DC Purple Line Cost Overruns and Delays Continue

by March 11, 2024
March 11, 2024
DC Purple Line Cost Overruns and Delays Continue

Marc Joffe

The Maryland Department of Transportation recently announced yet another delay of the Purple Line’s opening to Winter 2027, five years after its initially planned completion in 2022. The 16.2‑mile light rail project, which will connect New Carrollton and Bethesda in Washington, DC’s northern suburbs is also way over budget.

The full extent of the Purple Line construction cost overrun is not fully known because it is embedded in an opaque Public Private Partnership (P3) relationship under which contractors are participating in the project. As originally planned in 2016, Maryland agreed to pay the contractor group $5.6 billion to build and operate the system for thirty years.

By 2022, contract amendments had increased this amount to $9.3 billion, but the portion of the increase attributable to construction cost overruns is not clear. The latest delay will add a further $425 million to the overall contract cost.

And this may not be the last delay or cost overrun that the project will experience. Maryland Transportation Secretary Paul Wiedefield was hesitant to commit to no more deadline extensions for the Purple Line opening. He considers it likely that further time and cost overruns can arise from testing the transit network’s systems, which evokes the eerie possibility of neighboring DC Metro’s $55 million project to fix wheels on its 7000‐​series fleet.

While the Purple Line’s costs were greatly underestimated, its benefits are likely to be vastly overestimated. Total projected Purple Line ridership was expected to be 69,300 in 2040. This estimate, dating to August 2013, was reached based on the assumption that Washington metro area transit ridership would steadily increase over time.

The opposite has turned out to be the case, with the decade of the 2010s seeing a downward trend in DC Metro ridership. The pandemic and the work‐​from‐​home trend have further reduced ridership. DC Metro ridership in 2023 was only 50.6 percent of that of 2012, which would have been the most recent available ridership data at the time of the estimate’s publication. Notably, the Metro stations that lie on the Purple Line (New Carrollton, College Park, Silver Spring and Bethesda) now see even smaller proportions of their 2012 ridership than the system overall (32 percent, 40 percent, 45 percent and 41 percent, respectively).

The Purple Line also is not expected to offer substantial time savings for riders between WMATA stations. The above chart compares the estimated Purple Line travel times between transfer stations to the DC Metro with the travel times on existing WMATA service at 5:00 p.m. on weekdays. In fact, in some cases, the Purple Line takes longer than existing transit options, such as the trip from Silver Spring to College Park, and the trip from Bethesda to New Carrollton, both of which would be trips more quickly made on the DC Metro. In fact, the only station pair that would see more than a 20 percent reduction in time due to the Purple Line is the trip from Bethesda to Silver Spring, which is a route well‐​served by frequent bus service that takes at most 24 minutes during peak hour. While the current bus route from College Park to New Carrollton runs infrequently, under the no‐​build option for the Purple Line the frequency of that bus would increase from every 30 minutes to every 10 minutes.

Despite these concerns, the project is very unlikely to be stopped, as it is more than 65 percent complete. The Purple Line serves as a costly reminder of what not to do. Maryland policymakers should reconsider other costly rail transit ideas, such as the Baltimore Red Line or an extension of the Purple Line further into Prince George’s County or Virginia.

If Maryland does go ahead with other projects. It should reconsider its P3 model. The main benefit of P3’s is the transfer of risk from taxpayers to contractors. In this case, it appears that the private participant is being allowed to shift cost overruns to the state agency. Under a best practice P3 agreement, the private entity would absorb cost overruns along with the impact of lower‐​than‐​expected ridership.

The author would like to thank Cato Research Associate Jerome Famularo for his help with this post.

0
FacebookTwitterGoogle +Pinterest
previous post
Demystifying the Customs Clearance Process (Imports): A Guide for UK SMEs
next post
Companies run by women are less likely to go insolvent than companies run by men

You may also like

New Year, New AI Policy?

January 14, 2025

Minnesota Repeals Its Drug Paraphernalia Laws

May 24, 2023

Maui Wildfire Response Sure Looks Like Government Failure

August 21, 2023

The Court Cuts Injunctions Down To Size

June 30, 2025

The Penalty on American Savers and How USAs...

September 26, 2024

Congress Must Cut and Reform Medicaid

April 28, 2025

Senate to Hold Hearings on “Youth Vaping Epidemic”...

June 11, 2024

A Setback for Election Reformers?

November 20, 2024

Friday Feature: Colossal Academy

July 28, 2023

The Indefinite Suspension of All Refugees Is Unjustified

January 27, 2025

    Get free access to all of the retirement secrets and income strategies from our experts! or Join The Exclusive Subscription Today And Get the Premium Articles Acess for Free

    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.

    Recent Posts

    • Why More Businesses Are Choosing a Fractional CMO Instead of Agencies and Junior Hires

      July 19, 2025
    • ‘Get a job’: Medicaid work requirements included in Trump’s megabill sparks partisan debate on Capitol Hill

      July 19, 2025
    • Trump has now been in office for six months, for the second time. Here are the highlights

      July 19, 2025
    • Week Ahead: NIFTY Violates Short-Term Supports; Stays Tentative Devoid Of Any Major Triggers

      July 19, 2025
    • Slovenia approves law to legalize assisted dying for terminally-ill adults

      July 19, 2025
    • Heritage Foundation founder Edwin J. Feulner dies at 83

      July 19, 2025

    Categories

    • Business (8,525)
    • Investing (2,134)
    • Politics (16,122)
    • Stocks (3,221)
    • About us
    • Privacy Policy
    • Terms & Conditions

    Disclaimer: futureretirementsuccess.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

    Copyright © 2025 futureretirementsuccess.com | All Rights Reserved